Easilift's biggest load July 1st 2011 Reported to be the largest single
order ever placed in the UK for its
loading bay equipment, Easilift
Loading Systems has recently
completed a bespoke solution for
Tesco's new grocery distribution
centre in Daventry
Easilift, already an existing supply
partner to Tesco, was recruited to
take care of the 800,000ft2 facility's
widespread and complex loading
dock requirements.
Working closely with Tesco and
the main contractor Volker
Fitzpatrick, Easilift project-managed
the installation of 40 double deck
lifting platforms and 100 dock
leveller bays, all housed in external
loading pods.
Each of the double deck bays
incorporates a heavy duty, surface
mounted 16,000kg lifting platform,
capable of carrying up to 30 roll
cages. More articles from Easilift Loading Systems Ltd: |