Bitter boiler July 1st 2007 FMA has replaced several boilers
at InBev's Wellpark brewery, with
three NOx models previously used
at the Boddington's Strangeways
site in Manchester. FMA's remit
also involved the detailed re-design
of the flu gas system,allowing for
the future accommodation of
economisers and ensuring that the
correct emission criteria was
achieved. FMA put in place a
control system geared to ensuring
optimum efficiency and lifespan,
with all efficiency data being
captured and reported. The
brewery was kept running
throughout the entire upgrade
procedure, achieved via the
installation of a temporary boiler
which supplemented steam release
capability while each pair of old
boiler units was replaced. More articles from FMA Process Engineering Ltd: |