Register | Login | Set as Home Page | Bookmark | General Enquiries | Help | Sunday, 23rd of November 2008
IPE Logo
ipesearch.com
Search 
Magazine 
Register for our ENewsletter
Click to visit http://www.ni.com/vision/

What next?
 Request further Information    visit web site     Send to friend
 ABB Limited company's profile


Click to visit sponsors web site

Click to visit sponsors web site

Click to visit sponsors web site

Click to visit sponsors web site

Click to visit sponsors web site

Click to visit sponsors web site

Click to visit sponsors web site

Click to visit http://air.irco.com/uk/

Click to visit sponsors web site

Click to visit sponsors web site

Machine Building 2009
MTec 2009



Click here for the latest compressed air news !

Maintenance bill cut by 10%
September 1st 2008

ABB says maintenance costs at PolymerLatex UK site have fallen by more than 10% following work carried out by ABB's full service TM team.The achievement comes in the second year of a five-year performance based contract to manage PolymerLatex's entire UK maintenance operations at its site in Bromsgrove, Worcestershire.

The site specialises in the production of polymer products and other lattices for diverse applications.

ABB is responsible for all maintenance-related activities and equipment at the plant. It manages the operations against agreed targets and incentives for plant performance and total cost of maintenance.

PolymerLatex UK had identified by internal benchmarking the need to bring its maintenance operation to current best practice.

"The benefit of using ABB full service TM was that they could provide an overview of best practice from all over the world," explains Andreas Ostrowicki, MD PolymerLatex UK. "Our old system of maintenance was too reactive.

ABB has helped us identify faulty equipment, installed systems designed to drive costs down and implemented a truly proactive approach in maintenance." As well as improving maintenance procedures, ABB has introduced tools to measure plant efficiency such as Overall Equipment Effectiveness (OEE).

"Initially ABB has helped our manufacturing improvement teams to work better and introduced some valuable ideas to improve manufacturing efficiency," says Ostrowicki. The contract is based on a five-year improvement plan.