Register | Login | Set as Home Page | Bookmark | General Enquiries | Help | Sunday, 23rd of November 2008
IPE Logo
ipesearch.com
Search 
Magazine 
Register for our ENewsletter
Click to visit http://www.eriks.co.uk/bigplus/


Click to visit sponsors web site

Click to visit sponsors web site

Click to visit http://air.irco.com/uk/



Click to visit sponsors web site



Click to visit sponsors web site

Machine Building 2009
MTec 2009



Click here for the latest compressed air news !

Providing the space to maintain maintenance
March 1st 2008

The Prestwick operation of GE Caledonian will be the sole maintenance and repair centre for the new GEnx engine for the Boeing 787.

With the facility in Ayrshire already overhauling and repairing aero engines and component parts, an extension to the infrastructure was required to keep the company as a leading aerospace maintenance and overhaul hub.

An immediate requirement was for a modern, clean warehouse to store engine tooling to allow the transition from the current product line to the new engine type over a three-year period.

CG Flooring Systems has completed its largest and most demanding project. It has upgraded the 6000m2 floor of an iron foundry to narrow-aisle warehouse standard for racking to 12m high in less than six weeks.

As part of a re-organisation of its operations, Baxi Group, maker of space and water heating products, decided to close its cast iron foundry near Preston and use most of the building as its central warehouse.

A floor survey highlighted several challenges, including seven large pits up to 3m deep, vertical steel columns, horizontal Ibeams and steel bolts within the floor, damaged expansion joints, and low and high areas throughout the building.

All columns, beams and bolts were removed, and 150 linear metres of expansion joints were repaired. Pits were filled with consolidated hardcore, and then covered with a waterproof membrane and mesh reinforcement. The edges were cut to provide clean, vertical surfaces, and then 1000 600mm long dowel bars were inserted in the walls to provide a load transfer mechanism. Almost 100m3 of concrete was poured in 5h to bring the pits to floor level.

Elsewhere, a base screed was used to build low areas to floor level; high areas were scabbled to lower them. The entire area was then shot-blasted. The surface, a nominal 10mm-thick pumped cementitious screed, was completed in five days. Once cured, floor joints were transferred through and sealed to reduce the potential for cracking. Finally, a clear acrylic seal was applied to the entire surface.

Waste unit IP65 luminaire Comfort zone Stertil Stokvis offers a proactive, well-planned maintenance regime for loading bays that is designed specifically around a company's operations.

Such a regime is said to guard against breakdowns and keep the employer abreast of the latest regulations and health and safety requirements.

Appreciating that breakdowns don't always occur between 9 and 5, Monday to Friday, the company says it will provide a fast response when it is needed. Its engineers carry an extensive range of parts to enable them to carry out 'first time repairs'. If a company is busy at set times of the day, Stertil Stokvis will work outside those times to ensure minimum disruption.

Rubb Buildings met the challenge by providing a BVI-type building of 12 by 48m with 6m high side walls.

Access to the building is via an electric 5 by 5m roller shutter door. Due to tight site restraints, GE Caledonian required a change in the building size, reducing the span from 13.5 to 12m.

Rubb was able to accommodate this change to the construction late in the project due to the flexibility of the design and its manufacturing capability.

More articles from Rubb Buildings Limited: