Improved pre-treatment performance

16 March 2015

Delivered in just two weeks, Ondeo Industrial Solutions, part of Degrémont Industry, has provided EDF Energy with a water treatment system that has significantly improved pre-treatment plant performance.

During the time window provided by the O-Mobile units, Ondeo completed recovery works on the existing pre-treatment plant, which was required to run at full capacity during this period of high demand.

Following a comprehensive review and consultation with EDF, Ondeo replaced the treatment plant’s Sand Filter Media with an improved three-layer Multi Media and all resins in each vessel were moved to a wash tank and cleaned before being replaced.

 