In January 2009 Deal Distribution asked FACE Middle East Fzc to design the floor in its proposed VNA extension.With a racking top beam height of 11.7m, floor flatness was critical and the decision was made that in order

In January 2009 Deal Distribution
asked FACE Middle East Fzc to
design the floor in its proposed VNA
extension.With a racking top beam
height of 11.7m, floor flatness was
critical and the decision was made
that in order to satisfy the tight
project schedules, the 3600m2 floor
would be constructed using a Laser
Screed and then Laser Ground
within the aisles where necessary.
Once the design was finalised, the Concrete Grinding team spent three days preparing the sub-base.Within this time, the concrete mix design was tested and MB Mix was chosen to supply the concrete for the project. Once the levelling and compacting operations were completed, the concrete was ordered and floor construction began. Over three days, 1200m2 of floor was constructed each day. The finished floor levels were carefully monitored throughout construction and each slab was surveyed the day after casting for immediate feedback.
Once the design was finalised, the Concrete Grinding team spent three days preparing the sub-base.Within this time, the concrete mix design was tested and MB Mix was chosen to supply the concrete for the project. Once the levelling and compacting operations were completed, the concrete was ordered and floor construction began. Over three days, 1200m2 of floor was constructed each day. The finished floor levels were carefully monitored throughout construction and each slab was surveyed the day after casting for immediate feedback.