Edward Lowton
Editor |
![]() ![]() |
Home> | Plant, Process & Control | >Pumps | >Over-pumping solutions aid expansion project |
Over-pumping solutions aid expansion project
31 July 2019
Sykes Pumps has devised solutions for two over-pumping applications at Jaguar Land Rover's Whitley site expansion.

Jaguar Land Rover was given the go-ahead to invest £500 million into a 60-acre site adjacent to its current buildings in Whitley.
As part of a long-term growth strategy, the company decided to extend its already-substantial powertrain building in the area in which the company’s global headquarters are located.
This move is part of a wider commitment to improve its advanced engineering and design centres which, in turn, will accelerate the development of autonomous technology.
Jaguar Land Rover engineers based at the facility develop and refine various components responsible for generating the power for their vehicles, including the engine, transmission and drive shafts.
The approved construction plans will lead to the creation of almost 10,000ft2 of space, including a new 220-space car park.
The sheer scale of the project rendered it necessary for external contractors to be drafted in – with Sykes Pumps quickly on the scene.
It was quickly assessed that the Whitley site’s existing drains would be unable to cope with the additional capacities projected once everything has been completed. Upgrades to the original layout were therefore urgently required and these would complement a newly-installed drainage system which would need to be constructed before anything could proceed at ground level.
There were various aspects to Sykes’ intervention, with heavy rainfall contriving to make things more difficult on what was already a challenging assignment.
In the first instance, a Sykes P1001 3in electric submersible drainer pump powered by a generator was required to intercept dirty water from a storm drain and over-pump it approximately 80m away. The pump can handle flows of up to 20L/s and was fitted with a float system to facilitate automatic stop/start operation.
By utilising a submersible unit in this manner, Sykes was able to facilitate vital restoration works without impeding the overall functionality of a critical amenity. The chosen course of action also circumvented potential access issues, with narrow openings restricting the use of large industrial equipment.
The second phase, requires the installation of utility services before the construction of a new steel-framed factory extension can begin.
As a result, a Sykes GP100M 4in diesel driven pump was required to over-pump wastewater from a sewer on site and divert it 130m to a nearby manhole. It was imperative that a pump with solids handling capabilities was recommended as large quantities of sewage need to be moved to another part of the system. The selected pump can divert up to 45L of sewage per second of operation. This setup allows preordained sections of the prevailing sewer to be bypassed while improvements are carried out.
Chris Graham, sales director, comments: “Our pump expertise, skillset and local knowledge mean we can visit sites quickly, assess situations on an individual basis and respond to clients’ needs by providing them with the most efficient solutions. The extensive range of Sykes pumps and accessories is available for hire 24/7 throughout our national network of depots, meaning emergency cover is always on hand.
“Although the Jaguar Land Rover project is of an extremely high profile, the work we’re in the process of carrying out is very typical of the sort of thing we do day in, day out. We pride ourselves on having a flexible approach to overcoming just about every conceivable pump-related issue, with this outlook helping a big-name client progress with one of the most significant infrastructural jobs in the Midlands at present.
“We sent an engineer to the customer’s location to gain a better understanding of their requirements which pre-empted the deployment of the pumps currently in operation. Their presence on site has enabled things to advance on schedule and precedes a major construction strategy that will soon begin to take shape.”
- Surface-mounted auto-prime pump
- Over pumping for process critical sludge management
- Flood resilience: What you need to know
- Pump firm makes a splash for Wales Rally GB
- Same day overpump solution for East London sewer.
- Rapid response pump unit
- Pump ancillaries
- Fuel efficient low noise pump
- Diesel pump joins hire fleet
- Hydraulic submersibles